Ringling Blvd & Pine Place Roundabout

A new modern roundabout at the intersection of Ringling Blvd and Pine Place. This intersection reconstruction project marks the end of a string of roundabouts stretching west to Palm Ave. Additional Features installed during the reconstruction of the intersection included:
- Newer, safer access to the post office parking area.
- Removal of unsightly span wire and signal lights
- Landscaped center island of the roundabout and the four adjacent corners.
- Enhanced irrigation and storm water drainage facilities.
- New and replacement light poles.
- Paver brick crosswalks at the four legs of the roundabout, truck apron, and island approaches.
- In-road warning lights controlled by automatic activation bollards at the crosswalks.
- New Breeze Transit bus stop & transit shelter with dedicated bus pull-off
- Milling & resurfacing of all intersection approaches
- Striping and markings matching the bicycle and pedestrian enhancements to the Ringling Trail

Status
The Roundabout was opened to the Public on February 3rd, 2025.
Documents
Project Details
Project Manager
Erik Isern
(941) 263 - 6138
Erik.Isern@SarasotaFL.gov
Design Consultant
Kimley Horn & Associates, Inc.
Contractor
Ajax Paving Industries of Florida
Design Contract Cost
$282,750.00
Construction Contract Cost
$3,722,466.00
Project Schedule
Design Start
January 2021
Design Finish
August 2022
Construction Start
April 2024
Construction Completion
February 2025