Since Hurricanes Helene and Milton hit Sarasota, the majority of local businesses have reopened successfully. Residents have largely returned to their daily routines and tourism is rebounding, bringing visitors back to the City of Sarasota. Despite these positive developments, substantial repairs are still necessary, especially at waterfront parks and public facilities. Thank you for your continued patience as we work to restore Sarasota’s waterfronts, parks, and public amenities following Hurricanes Helene and Milton.
We understand the community’s desire to see these spaces restored quickly. However, the City is committed to rebuilding safely, sustainably, and in full compliance with state and federal requirements. Here's why many of these recovery projects require careful sequencing:
Below is a summary of where each project stands, what steps remain, and when you can expect construction to begin. Following permit approvals and contractor procurement, construction is anticipated to begin in early 2026, with a total estimated cost for repairs of $17.4 Million.
Approved
Construction paused due to partial government shutdown
Late 2026
Early 2027
Pre-Construction -Finalizing agreement with FDOT
Late 2027
Late 2028
Pre-Construction - Start delayed due to partial government shutdown
Early 2028
Late 2026/Early 2027
Pending
Design
2029 (dock only)
2031 (Dock & Shop/Restroom)
Late 2026/Early2027
Mid 2027
Completed
January 2026
Complete
April 2026
Permitting